Exhibiting at Bharat Mandapam, Pragati Maidan, calls for more than approving an attractive booth concept. Design submissions, contractor coordination, material movement, services, and installation need to work as one project.
This guide helps exhibitors organise that project. It does not replace the current event manual or establish universal construction heights, entry gates, loading limits, service charges, or access hours. Obtain the instructions applicable to your actual booking before committing to production or dispatch.
Start with the organiser and official ITPO resources
ITPO’s official venue information identifies Bharat Mandapam at Pragati Maidan, New Delhi, within its venue operations. ITPO also publishes resources covering venue planning and services.
Its published licensing and facilities guide includes sections on architectural and engineering guidelines and the entry of vehicles carrying exhibition material. Confirm the applicable current version and event instructions with your organiser rather than treating an undated downloaded document as the final authority.
Keep the booking confirmation, event exhibitor manual, floor plan, service forms, and contractor instructions together. Resolve unclear or conflicting requirements in writing.
Confirm the hall, footprint, and booking scope
Record your actual hall, stall number, allotted dimensions, open sides, and booking type. Ask what structure, furniture, flooring, graphics, lighting, and services are included.
Do not infer the package from a promotional photograph. A shell-scheme booking and a bare-space booking may require different design and supplier arrangements.
Give the designer the current floor plan and relevant booking documents. Review the visitor approach, neighbouring boundaries, and known service positions using the information actually supplied.
Build a design-review question list
Ask the organiser what drawings, specifications, contractor details, and other documents are required for the proposed booth. Assign an owner to each submission and record the applicable deadlines.
- Which construction and graphic instructions apply to the booked space?
- What review is needed for platforms, tall features, or overhead signage?
- How should equipment and service requirements be documented?
- Which materials or on-site work processes need specific confirmation?
- What evidence of acceptance is required before fabrication or installation?
- How are later design changes reviewed?
A submitted drawing is not necessarily an accepted drawing. Keep confirmation with the final design package.
Plan the visitor experience inside the allotted space
Define the main objective and choose the activities that support it. Make room for introductions, product discovery, demonstrations, and meetings according to the actual brief.
Show where staff stand, where visitors gather, and how chairs move. Do not size the layout around furniture footprints alone.
Have the responsible professionals review access, level changes, equipment separation, and other relevant technical matters against applicable instructions. An open-looking render is not evidence that those questions are resolved.
Distinguish fabrication from on-site installation
Ask what work may be carried out at the venue and what must arrive prepared. Do not assume that workshop activities are permitted in the hall.
Have the fabricator plan production, packing, assembly, and finishing around the confirmed event instructions. Identify how modules and graphics will be labelled so the team can locate them without opening every package.
Do not improvise a prohibited or unreviewed process on site because a component was not prepared in advance. Escalate the issue through the responsible project lead.
Confirm contractor responsibilities
Identify who supplies design, structure, graphics, flooring, furniture, AV, electrical work, logistics, handling, cleaning, and supervision. Confirm any organiser-appointed or venue-controlled work packages.
Give every supplier the same current layout and schedule. Nominate one exhibitor-side decision-maker to approve changes and resolve scope gaps.
For tasks requiring specialist competence or authorisation, have the responsible project team verify the appropriate provider. General helpers are not interchangeable with electricians, riggers, or equipment operators.
Obtain the material-access process before dispatch
Ask the organiser for the current process for goods vehicles, contractor entry, material documentation, receiving contacts, delivery windows, and movement into the booked hall.
Confirm the applicable gate and route for the actual delivery. Do not send a driver using an old map or a previous show’s instructions without verification.
Record who meets the shipment, who checks quantities and condition, and who has authority to resolve an unexpected access problem.
Share accurate shipment information
Provide the logistics and handling providers with package dimensions, weights, fragility information, equipment configuration, and relevant manufacturer handling documentation.
Have them review the actual route and final positioning arrangements. A machine fitting inside the stall footprint does not establish that it can reach the stall through the planned route.
Confirm handling equipment, competent personnel, and required approvals through the responsible providers. This guide does not specify lifting methods, crane selection, or floor capacities.
Plan staging and packaging
Agree where materials may wait and where empty packaging will go under the current event arrangements. Keep staging from becoming an unplanned extension of the booth.
Label returnable items, rental accessories, and packaging clearly. Record who collects empties and who brings them back for dismantling where such a service is arranged.
Ask the organiser how waste and leftover materials must be managed. Do not assume they can be left behind or placed wherever space appears available.
Coordinate power and other services early
Prepare an equipment list covering displays, screens, lighting, demonstrations, and other service-dependent items. Have qualified providers assess the actual requirements.
Confirm who orders the event service, who supplies the connection, who installs the booth-side arrangement, and who performs relevant checks. Do not choose a power requirement by copying another stall.
Ask about any additional services needed for your project and record availability, scope, deadlines, and separately quoted work. Keep technical decisions with the responsible specialists.
Build the schedule around dependencies
Coordinate venue protection, large deliveries, equipment placement, services, structure, finishes, graphics, furniture, and cleaning. Ask each supplier to identify when its area is ready for the next team.
Allow time for review and correction before opening. Delivery completion and decorative completion are not the same as a finished handover.
If a delay occurs, have the project lead revise the sequence. Extra manpower does not resolve every missing delivery, access issue, or unavailable technical service.
Compare the full installed cost
- Design, drawings, revisions, and coordination.
- Structure, materials, flooring, graphics, and lighting.
- Furniture, AV, approved content, and accessories.
- Event services and separately ordered work.
- Transport, access coordination, handling, and placement.
- Supervision, relevant checks, cleaning, and handover.
- Show-day support, dismantling, packing, and collection.
Ask providers to identify exclusions, quotation validity, substitutions, and the change-approval process. This guide does not establish current ITPO charges, event fees, deposits, or local supplier prices.
Record the pre-opening handover
Walk the booth with the responsible leads. Check the actual layout, graphics, furniture, equipment, and outstanding work against the agreed scope.
Have the appropriate professionals complete required technical checks. Record the support contact and any limitations relevant to normal booth operation.
Brief staff on visitor routing, appointments, product handoffs, and fault reporting. They should not modify technical installations or attempt unfamiliar repairs.
Arrange dismantling before the show begins
Confirm the event-specific timing and sequence for appropriate shutdown, specialist disconnection, removal, return packing, and collection.
Identify who checks rental quantities, accessories, keys, and condition at return. Keep product inventories separate from the fabricator’s equipment list.
Do not assume public closing time authorises immediate removal or that arrival instructions automatically apply to departure. Obtain the actual dismantling process.
Bharat Mandapam exhibitor checklist
- Confirm the booking details and included items.
- Obtain applicable current venue and event documents.
- Assign design, contractor, and service submissions.
- Approve a practical layout and accurate equipment schedule.
- Confirm material-access instructions before dispatch.
- Coordinate receiving, handling, staging, and packaging.
- Plan services and the build sequence with responsible providers.
- Compare complete costs and record exclusions.
- Complete checks and the pre-opening handover.
- Confirm support, dismantling, and return collection.
Frequently asked questions
What booth height is allowed at Bharat Mandapam?
Confirm the limit and any review conditions for your actual event, hall, and booking. This guide does not establish a universal height.
Which gate should our material vehicle use?
Obtain the current goods-access instructions from the organiser for the specific delivery. Do not use a gate number from another event without confirmation.
Can we use our own stall fabricator?
Ask about contractor eligibility, registration, submissions, and permitted scope. This guide does not establish permission for a particular provider.
Is electricity included in the stall booking?
Check the written booking and service scope. Confirm both the ordered service and responsibility for the installation within the booth.
Can we finish fabrication inside the hall?
Confirm the permitted on-site processes before dispatch. Have your fabricator plan around the actual instructions rather than assuming workshop activity is allowed.
Make the paperwork and physical plan agree
A well-run Bharat Mandapam exhibition project connects a clear design with current instructions, coordinated suppliers, and a realistic material-movement plan. Resolve responsibilities early, document decisions, and review changes before they reach the venue.
Official references
ITPO official exhibition venue information
ITPO published licensing and facilities guide: confirm applicable current version
ITPO facilities and services information